AL RAHA LOFTS ONE

Al Raha Lofts is the group’s first development in the highly sought-after area of Al Raha Beach residences have expansive views over either the canal, or the main boulevard and offer ample parking for all the apartments. The dynamic design of Al Raha Lofts complements each other with their cascading fades enticing residents towards the waterfront promenade.

504 (Raha 1) (2B+G+6) – Progress 57.00 %
  • Block work for 6th floor is completed.
  • Plaster of 1st floor is ongoing (completed 30%).
  • MEP 1st fix at 1st floor is ongoing (completed 70%).
  • MEP 2nd fix is ongoing at basement 2 up till 5th floor (completed 10%).
VIEW MORE

AL RAHA LOFTS TWO

Al Raha Lofts is the group’s first development in the highly sought-after area of Al Raha Beach residences have expansive views over either the canal, or the main boulevard and offer ample parking for all the apartments. The dynamic design of Al Raha Lofts complements each other with their cascading fades enticing residents towards the waterfront promenade.

503 (Raha 2) (2B+G+6) – Progress 62.00 %
  • Plaster works at 4th floor is ongoing (completed 80%).
  • Plaster preparation at 5th floor is ongoing (completed 80%).
  • MEP 1st fix work at 5th floor is ongoing.
  • MEP 2nd fix is ongoing at basement 2 up till 2nd floor (completed 25%).
  • Steel stairs installation inside duplex units in 1st floor is ongoing (completed 70%).
  • Ceramic tiles fixing inside apartments is ongoing (completed 60% at ground floor and 30% at 1st floor).
  • Curtain wall installation is ongoing (completed 40% at ground floor, 20% at 1st floor and 30% at 2nd floor).
  • External plaster is ongoing (completed 60%).
VIEW MORE

OASIS RESIDENCES ONE

Ideally situated, this development takes pride of place on the ‘green finger’, a luscious landscaped area which carves through the center of the residential district of Masdar City. Situated between this green oasis and the shopping mall, the location lends itself to all the recreational and leisure facilities that Masdar City has to offer.

G04A (Oasis 1) (3B+G+10) – Progress 50 %
  • Ninth floor slab casting completed
  • Ninth floor vertical elements completed
  • Roof floor slab shuttering ongoing
  • Roof floor slab casting ongoing
  • Block works and MEP first fix in basements 1, 2 and 3
  • Block works and MEP first fix in Ground, First, Second, Third, Fourth, Fifth and sixth floors
VIEW MORE

OASIS RESIDENCES TWO

The different selection options of apartments allow residents the possibility of choosing according to their own needs and preferences. Oasis Two offers contemporary studios that are fully equipped with elegantly designed interiors to suit the personal proclivity of all our clients.

G04B (Oasis 2) (2B+G+9) – Progress 10 %
  • Mobilization is ongoing (completed 40%).
  • Installation of dewatering system is completed and operating.
  • Excavation to piling platform is ongoing (completed 70%).
  • Piling work is ongoing (completed 50%).
VIEW MORE

Maryah Vista

Maryah Project – Progress 5.5 %
  • Mobilization completed.
  • Fence and Sign board completed.
  • More than 90% of shoring (secant piles) completed.
VIEW MORE

Alexis Tower Dubai

Reportage developments is proud to introduce Alexis Tower Residence, a highend residential apartment building with facilities in Downtown Jebel Ali district of Dubai.

Plot 27 (Alexis ) (3B+G+3P+13) – Progress 12.5 %
  • Mobilization is completed.
  • Soil Investigation is Completed.
  • Shoring – Guide wall completed.
  • Shoring – completed.
  • Piling work – foundation – 100% completed.
  • Capping beam works completed.
  • Pile test completed.
  • Dewatering networking preparation 80% completed.
VIEW MORE

The Gate Residence

The latest project development design from Reportage Properties is for a multipurpose ‘complex’ within Masdar City which features six core buildings. Implementing an urban design strategy of a ‘town square’ reinforces the Masdar City Master Plan for developing a community.

B01 (The Gate) (B+G+8) – Progress 13.5 %
  • Mobilization is ongoing (completed 25%).
  • Installation of dewatering system is completed and operating.
  • Site works (excavation, backfilling and compaction) is ongoing (completed 75%).
  • Blinding and solid block work for pile caps is ongoing.
VIEW MORE

Rukan Dubai

Rukan – Progress 4.00 %
  • Soil Investigation is on-going.
  • Mobilization is on-going.
  • site grading is ongoing.
  • fencing works is ongoing.
  • signboard works is ongoing.
VIEW MORE